18-03-2020
2.26.12 |
“the exercise
after the Base Date by the UK government of any statutory power which directly
affects the execution of the Works”. |
2.26.14 |
Force majeure |
What is likely to happen?
In the first case, the Government might force
construction sites to close using statutory powers if there is a “lock down”,
in the absence of an agreement to suspend the works this event is relevant and if very clear will entitle the
contractor to an ‘Extension of Time’.
In the second case, the concept of “force majeure”, varies by civil
jurisdiction. In English law, force majeure is not defined, either in statute
or under case law, and notably, the JCT does not provide any contractual
definition of force majeure either.
Typically, an event of force majeure is an event that is beyond
either party's control, not attributable to either party, and could not reasonably
have been foreseen, avoided or overcome.
Will the Coronavirus amount to force majeure? There are
no reported cases of the scope of the "force majeure" term being
tested in respect of a JCT contract. As such without the JCT providing a contractual
definition and without legal precedent, the full scope of the force majeure
provisions and how this applies to the coronavirus crisis may require
determination by future case law.
However, guidance may be identified in the case of McCardie J in Lebeaupin v Crispin [1920] 2 KB 714 which suggests that an epidemic may constitute a force majeure event:
"Force majeure. This term is used
with reference to all circumstances independent of the will of man, and which
it is not in his power to control... epidemics are cases of force majeure…"
As such it certainly appears reasonable for contractors
to turn to the force majeure relevant event in respect of the effect of the
Coronavirus.
Other Instances
Suspension of construction works
If the works are suspended by agreement or otherwise,
just be aware that JCT contracts contain rights to terminate by either party if
the period of suspension is prolonged.
In the JCT Design & Build 2016 contract, clause 8.11 allows
termination on 7 days notice after the expiry of the “relevant period of
suspension”, which can be found in the articles section under 8.11.1.1 to
8.11.1.6, which if left blank is two months by default. If left blank, either party can terminate the
contract on 7 days notice after two months has expired for both instances of
Government intervention/shutdown and force majeure (should the Coronavirus be
accepted as such).
Walk out
Despite the world closing down, contractors must be careful
not to just walk off site. An argument could
be raised by the paying party that repudiatory breach has occurred. Termination with damages could then be
claimed. It is thus very advisable to
arrange any shut down with the other party or serve them with the appropriate notice.
Solutions
Where an ‘Extension of Time’ is granted after the Coronavirus
crisis is over, the contractor will not suffer any liquidated damages, however,
any costs incurred due to the disruption and delay will not be recoverable by
the contractor as the government lock down or force majeure events are cost
neutral, it was nobody’s fault. In the
case of termination, the contractor must vacate the site and submit a final
account to include the value of works carried out, any relevant losses and
expenses, costs of demobilisation and any materials and goods ordered and
legally bound to pay. The Employer makes
an assessment and a payment, if applicable, within 28 days of receipt of the
accounts from the contractor. A formal
settlement agreement is recommended here to avoid dispute.
The Effect of Coronavirus on the Construction Industry
The effect of Coronavirus and construction project shutdown
is going to be devastating for the construction industry as margins are always
tight and the flow of cash is paramount.
If the cash does not flow down the payment chain and none can be earned
the contractor’s cash flow will grind to a halt and create insolvent positions,
which will be more acute if the contractor has numerous projects all shut
down. As noted above, there is possible
prospect of compensation for the losses incurred, although there is nothing to
stop claims and if terminated a valuation of losses can be advanced. Resolving cash flow will be critical on shut
down, adjudication is a way of forcing that process, and Arbicon are leading
advocates in the adjudication process and negotiation available to provide
guidance through what will be a very difficult path for most contractors.
The JCT Contract reflects most principle terms in other
contracts used in the construction industry such as NEC Contracts. If you need specific advice on your contract
please do let us know.
Arbicon can assist in the management of all notices, agreements and settlements or handle any disputes that arise thanks to Covid-19! Get in touch with our expert team for more help or advice by using our contact form or calling our offices on:
01733 233737 Peterborough
0207 406 1494 London
0121 262 4086 Birmingham