11-05-2020
The
likelihood is that contractors will be entitled to an extension of time, but if
it is granted it will be a neutral event so no costs can be recovered by either
party, but is a time extension set in stone?
You will have seen a number of articles online about how the pandemic is a force majeure which should allow the contractor to escape from the liability of delay. We have seen firms in recent weeks using the pandemic to escape from the blame of delay or worse repudiatory breach, but is this set in stone?
The
Government has been wishy washy about whether construction projects can
proceed, construction has been classed as essential and with social distancing
in place it can. The position has now perhaps changed after the Prime
Minister's speech (10th May) where he
clarified that construction most definitely can proceed. There is no doubt that
labour, plant and material sourcing has been difficult, but it has been
possible and many sources are open for business. So does this change the
entitlement to an extension of time for the pandemic?
Is
there now an argument that as work can proceed, is the force majeure claim
nullified? What is the status contractually? Where is the line drawn in the
sand?
The fact is most construction projects where social distancing can be done
probably now have no excuse for delay, each case however will be on its merits,
depending on what is agreed in the contract or what was agreed at the outset of
the lockdown. There will be examples where there are occupiers where work will
not be possible and others where no individuals are affected, the former is
likely to be a situation where an extension of time is allowed and the latter
may not have that privilege. Again it all depends on the contract and external
factors, it will not be straightforward as all construction contracts are
different. If it is found there is no extension possible then it may be held
that a repudiation has occurred, which could be a disaster.
If
you are a Contractor, are you really at risk of breach for delay and
repudiation?
Going back to the top of this article, the view now is that nothing is set in
stone where an extension of time is concerned in the current climate, that
means a risk of damages or liquidated damages for delays or damages for
abandonment/repudiation of the works. It is difficult to see what the
outcome might be from here onwards and if such disputes are likely you need to
be prepared. Contemporaneous evidence of actions and deeds will be essential
and a check on your current contractual position is advised.